Switch failover Remote Copy group

Procedure
  1. Perform switch failover on the Remote Copy group.

    After the switch failover is complete, the new primary rolls back as secondary. Similarly, the new secondary rolls back as the primary.

  2. Rescan the storage devices using the vCenter in secondary site.