Installation sequence

The HPE Telco Blueprint uses the NPS toolkit to deploy RHOCP. This deployment is categorized into four different stages:
  1. Pre deployment

  2. NPS deployment

  3. VIM deployment

  4. Post deployment

See Time matrix for installation sequence for the time taken to perform each step in the process.

Pre deployment

The following diagram illustrates the sequence of steps that must be completed during the pre-deployment stage:

Pre deployment sequence

NPS deployment

The following diagram illustrates the sequence of steps that must be completed to deploy NPS:

NPS deployment

VIM deployment

The following diagram illustrates the sequence of steps that must be completed to deploy VIM:


Post deployment

The following diagram illustrates the sequence of steps that must be completed during the post-deployment stage:

Telco Bleuprint post deployment process

Time matrix for installation sequence

Table 7: Time matrix for installation sequence for starter kit
Detailed tasks Deployment mode Duration (in minutes)
Pre deployment
Generate input JSON file using TICG Manual 40
Configure DNS Manual NA
Switch Pre-Configuration - (Core, Management, and Data Switches) Manual NA
Install NPS Host (OS installation) Manual 30
NPS Deployment
Prepare and deploy NPS Toolkit VM Automated 30
Install NPS toolkit Web API server and Redis Containers in NPS toolkit VM Automated 45
Upload input JSON file generated using TICG and validate JSON Automated 2
Deploy Switch Configuration Automated 10
Enable iLO DHCP service Automated 5
Prepare the hardware Automated 20
Deploy Image Service - Installation Automated 25
Deploy Image Service - Configuration Automated 7
VIM Deployment
vCenter Management server Automated 35
vCenter Resource server Automated 30
NSX-T Automated 30
VIO Automated 65
Deploying VMware Operations Management
Deploying vRealize Operations Manager Automated 20
Deploying vRealize Log Insight Automated 10
Deploying vRealize Orchestrator Automated 12
Deploying vRealize Network Insight Manual NA
Post deployment
Configure external DHCP server Manual NA
VMware post deployment customizations Manual NA
Shutdown and startup of VMware (optional) Manual NA
NOTE:

The total time taken for deploying VMware on a new environment (starter kit) is approximately seven hours.